Footing and foundation wall calculator
Concrete in cubic metres for a strip footing and foundation wall, with rebar and the formwork area.
Your job
Centre-line length of the wall.
200 mm (8 in) is common for a basement wall.
Foundation walls with exposure to freezing and de-icing salts are often specified at 32 MPa.
0 is not allowed; use a large spacing for lightly reinforced walls.
Answer
- Concrete to order
- 26.5 m³ (34.66 yd³)
- Footing
- 6 m³
- Wall
- 19.2 m³
- Form area
- 212 m² (footing 20, wall 192)
- Rebar
- 88 m 15M, 338 m 10M (403 kg)
- Footings must sit below frost depth on undisturbed soil; the depth is not part of this takeoff.
Method: Volume = length x width x thickness for the footing and the wall, plus waste; ordered in 0.25 m³ steps; Form area = both faces of the wall plus both sides of the footing; rebar masses 10M 0.785 kg/m, 15M 1.57 kg/m; Applicable foundation requirements in the building code adopted in your jurisdiction; confirm with the project drawings and authority having jurisdiction
Estimating aid based on a summary of the CEC. Provinces adopt different editions and amendments. Confirm with the authority having jurisdiction, and the engineer of record where one is involved.
Priced takeoff
- Ready-mix concrete 25 MPa, footing and foundation wall$5,353.0026.5 m3 at $202.0092.75 h
- Rebar 15M$218.2488 m at $2.484.4 h
- Rebar 10M$560.32337.54 m at $1.6613.5 h
- Formwork, footing and wall, both facesprice pending212 sqm127.2 h
- Materials
- $6,131.56
- Labour, 237.85 h at $105.00
- $24,974.25
- Your cost, before markup and tax
- $31,105.81
Reference prices are dated baselines (2026-11) for Ontario. Confirm them with your supplier. In TradeQuote PRO your own saved prices replace these.
How it works
You enter 10 inputs. The calculator returns the quantities, rounds them up the way the material is sold, and lists the takeoff so it can be priced.
- Total length of footing and wall (m). Centre-line length of the wall.
- Footing width (mm).
- Footing thickness (mm).
- Wall thickness (mm). 200 mm (8 in) is common for a basement wall.
- Wall height (m).
- Concrete strength. Foundation walls with exposure to freezing and de-icing salts are often specified at 32 MPa.
- Waste allowance (%).
- Continuous 15M bars in the footing.
- Wall vertical 10M bar spacing (mm). 0 is not allowed; use a large spacing for lightly reinforced walls.
- Wall horizontal 10M rows.
The method
- Volume = length x width x thickness for the footing and the wall, plus waste; ordered in 0.25 m³ steps
- Form area = both faces of the wall plus both sides of the footing; rebar masses 10M 0.785 kg/m, 15M 1.57 kg/m
- Applicable foundation requirements in the building code adopted in your jurisdiction; confirm with the project drawings and authority having jurisdiction
Check results against the code and manufacturer data that apply to your job. Prices are dated baselines to confirm with a supplier.
Add this to a real estimate in TradeQuote PRO
The takeoff lands as estimate lines with your prices, markup and tax, then becomes a proposal the client signs.
More concrete calculators
- Concrete slab calculatorCubic metres and yards of ready-mix for a slab, with rebar grid, gravel base, vapour barrier and finishing labour.
- Concrete pile and pier calculatorConcrete volume for round form-tube piles for decks and footings, as ready-mix cubic metres or 30 kg bags, with the tubes needed.